4.14 Condensate Extraction Pump Erection
Applicable scope:Be applicable to condensate pump erection,with the following inspection items:condensate pump inspection,condensate pump erection,condensate pump trial run.
4.14.1 Inspection and acceptance of condensate pump are given in Table 4.14.1.
Table 4.14.1 Condensate pump inspection

Table 4.14.1(Continued)

4.14.2 Inspection and acceptance of condensate extraction pump erection.are given in Table 4.14.2.
Table 4.14.2 Inspection and acceptance of condensate extraction pump erection.

4.14.3 condensate extraction pump trial run Table 4.14.3.
Table 4.14.3 Condensate extraction pump trial run