4.7 Water Cooled Condenser Assembly and Erection
4.7.1 Condenser(steam exhaust device)erection.
Applicable scope:applicable to condenser(steam exhaust device)erection,with the following inspection items:condenser(steam exhaust device)shell assembly,condenser(steam exhaust device)in place and alignment.
1 Condenser(steam exhaust device)shell assembly inspection and acceptance are given in Table 4.7.1-1
Table 4.7.1-1 Condenser(steam exhaust device)shell assembly

2 Condenser(steam exhaust device)in place and alignment inspection and acceptance are given in Table 4.7.1-2.
Table 4.7.1-2 Condenser(steam exhaust device)in place and alignment

4.7.2 Condenser cooling tube bundle erection inspection and acceptance are given in Table 4.7.2.
Table 4.7.2 Condenser cooling tube bundle erection

Table 4.7.2(Continued)

4.7.3 Condenser(steam exhaust device)and cylinder connection and leakage test inspection and acceptance are given in Table 4.7.3.
Table 4.7.3 Condenser(steam exhaust device)and cylinder connection and leakage test

4.7.4 Condenser(steam exhaust device)accessories erection and secondary grouting inspection and acceptance are given in Table 4.7.4.
Table 4.7.4 Condenser(steam exhaust device)accessories erection and Secondary grouting

4.7.5 Rubber ball cleaner inspection and erection inspection and acceptance are given in Table 4.7.5.
Table 4.7.5 Rubber Ball Cleaner Inspection and Erection

4.7.6 Mandatory provision implementation inspection of water cooled condenser assembly erection is given in Table 4.7.6.
Table 4.7.6 Mandatory provision implementation inspection table of water cooled condenser assembly erection subsection project